RECONSTRUCTION AND EXPANSION OF THE “AIZKRAUKLE” SUBSTATIONTilta street 2, Aizkraukle

Reconstruction of the “Aizkraukle” substation included dismantlement of the existing 110 kV substation (six connections). To replace it, a new 110 kV substation was built. The scope of works also provided  expansion of the existing 330 kV substation and installation of an autotransformer and a shunt reactor. Two more 330 kV connections were built in order to connect these facilities to the existing 330 kV substation.

Client:
“Augstsprieguma tīkls”, Jsc
Name of the project:
RECONSTRUCTION AND EXPANSION OF THE “AIZKRAUKLE” SUBSTATION
Category:
Civil engineering
Type of construction:
Power infrastructure
Designer:
“K2 projekts", LTd.
Description of work:
Reconstruction
Country:
Latvia
Adress:
Tilta street 2, Aizkraukle
Beginning of project:
2016
Completion year:
2019